砺志PMP模拟题每周精选之一之八
砺志PMP模拟题每周精选(之八)
(2003年5月5日-2003年5月11日)
Qustions1:
Aprojectisanidealenvironmentinwhichtousethetechniqueofmanagementbyobjectivesbecause--
a.Projectmanagementinvolvessettingorganizationalobjectives
b.Projectsgenerallyarehandledthroughamatrixmanagementenvironment
c.Projectmanagers'responsibilitiesaredefinedintermsofcorporateobjectives
d.Allprojectsshouldbestronglyorientedtowardgoalsandobjectives
Qustions3:
Allthefollowingareexamplesofbenefitmeasurementmethodsofprojectselectionexcept--
a.Benefit-costration
b.Paybackperiod
c.Peerreview
d.Multiobjectiveprogramming
Qustions5:
Whichofthefollowingisatoolortechniqueusedforprojectinitiation--
a.Alternativesidentification
b.Configurationmanagement
c.Decisionmodels
d.Decomposition
Qustions2:
Eachprojectphaseismarkedbycompletionofoneormoredeliverables.Thedeliverablefortheconceptphaseofaprojectisthe--
a.Projectplan
b.Statementofwork
c.Projectcharter
d.Resourcespreadsheet
Qustions4:
Changerequestsmayresultfrom--
a.Areviewoftheprojectcharter
b.Areviewoftheperformingorganization'sstrategicplan
c.Enhancedproblem-solvingskillsonthepartoftheprojectteam
d.Anerrororomissioninscopedefinition
Qustions6:
Theproject'sscopechangecontrolsystemis--
a.Acollectionofformal,documentedprocedurestodefinethestepsbywhichofficialprojectdocumentsmaybechanged
b.Adocumentedprocessusedtoapplytechnicalandadministrativedirectionandsurveillancetoidentifyanddocumentfunctionalandphysicalcharacteristicsofitems,recordandreportchange,controlchange,andaudittheitemsandsystemtoverifyconformancetorequirements
c.Asetofproceduresbywhichprojectscopemaybechanged,includingthepaperwork,trackingsystems,andapprovallevelsnecessaryforauthorizingchange
d.Mandatoryforuseonprojectssothatthescopemanagementplancannotbechangedwithoutpriorreviewandsign-off
砺志PMP模拟题本周精选(之七)
(2003年4月28日-2003年5月4日)
Qustions1:
Whichstatementaboutcustomerexpectationsisnottrue--
a.Theproductorserviceshouldbeusableasintended.
b.Contractualprovisions,includingscheduleandperformancestandards,shouldbemet.
c.Changesshouldbemadeimmediately,andallcustomerwantsshouldbesatisfiedwithoutbureaucratichassle
d.Thesellershouldassumetheresponsibilityofunderstandingcustomerneedsandaddressingthemeffectively.
Qustions3:
Thedocumentthatdescribestheobjectives,workcontent,deliverables,andendproductofaprojectisthe--
a.Projectcharter
b.Productdescription
c.Scopestatement
d.WBS
Qustions5:
Maintenanceiscruciallyimportanttoprojectsandshould--
a.Beincludedasanactivitytobeperformedduringthecloseoutphase
b.Haveaseparatephaseinthelifecycleininformationsystemsprojectsbecause60%to70%oflife-cyclecostsofcomputersystemsaregenerallydevotedtomaintenance
c.Notbeviewedaspartoftheprojectlifecycle
d.Alwaysbeviewedasaseparateproject
Qustions2:
TheWBSisaninputtoscopechangecontrolbecauseit--
a.Providesinformationonprojectobjectives
b.Definestheproject'sscopebaseline
c.Definesallprojectbaselines
d.Providesinformationonscopeperformance
Qustions4:
Whenanorganizationchoosesaprojectselectionmodel,themostimportantcriterionis--
a.Capability
b.Realism
c.Easeofuse
d.Cost
Qustions6:
Aprojectmanager'scompanyoperatesinahigh-technologyarearequiringtheintegrationandsharingofseveralfunctionalspecialties.Theprojectmanagerisconsideringtheappropriateorganizationalstructureofranewproject,thelikelychoicewouldbe--
a.Matrix
b.Tightmatrix
c.Functional
d.Projectized
砺志PMP模拟题每周精选(之六)
(2003年4月21日-2003年4月28日)
Qustions1:
Whichofthefollowingisanappropriatemanagementstyletousewhentheprojectmanagerwantstoencouragethestafftopoolitsknowledgetomakethebestdecisionpossible?
--
a.Laissez-faire
b.Democratic
c.Autocratic
d.Directive
Qustions3:
Whichofthefollowingsinotpartoftheprojectplan--
a.Theprojectcharter
b.TheWBS
c.Performancemeasurementbaselinesforscheduleandcost
d.Theprojectteammembers'compensationplan
Qustions5:
WhatareMaslow'sthreehighestlevelsofhumanneeds--
a.Physiological,safety,andsocial
b.Recognition,responsibility,andreward
c.Self-actualization,esteem,andsocial
d.Happiness,health,andprosperity
Qustions2:
Aprojectmanagementprocessandaproduct-orientedmanagementprocess-
a.Overlapandinteractthroughouttheproject
b.Aredefinedbytheprojectlifecycle
c.Areconcernedwithdescribingandorganizingprojectwork
d.Aresimilarforeachapplicationarea
Qustions4:
Controllingoccurs--
a.Onacontinualbasesthroughouttheproject
b.Attheendofeachphaseoftheprojectlifecycletoassessitssuccessinmeetingprojectobjectives
c.Attheendofeachplanningprocess
d.Onacontinualbasesthroughouttheexecutingprocessandasneededintheotherprocesses
Qustions6:
Organizationalinterfacesareprimarily--
a.Contractualinterfacesbetweenmorethatoneorganization
b.Managementdecisionsrelatingtotheresolutionofconflict
c.Personalinterfacesaddressingprofessionaldevelopmentprograms
d.Managementinterfacesdealingwithactions,decisions,orapprovals
砺志PMP模拟题每周精选之五
(2003年4月14日-2003年4月21日)
Qustions1:
Thepurposeofaprojectplanningmethodologyisto--
a.Provideastructuredapproachtoguidetheprojectteaminprojectplandevelopment
b.Ensurethatallrequiredformsarecompleted
c.Ensurethatorganizationalpoliciesandproceduresarefollowedduringthedevelopmentandexecutionoftheprojectplan
d.Serveasarepositoryoflessonslearnedthatcanbeappliedtothecurrentproject
Qustions3:
Accordingtotheexpectancytheoryofmotivation--
a.Poorperformanceisthenaturaloutcomeofpoortraining
b.Managersshouldnotexpecttoomuchofworkers
c.Motivationtoactislinkedtoanoutcomethatisexpectedtohavevalue
d.Managersshouldexpectthatemployeeswhoarepaidmorewillworkharder
Qustions5:
Whichofthefollowingisanexampleofa'soft'toolthatcouldbepartofaprojectmanagementmethodology--
a.Projectmanagementsoftware
b.Acontinuousimprovementtarget
c.Afacilitatedkickoffmeeting
d.Costaccountingcodes
Qustions2:
Lessonslearnedfromprojectsaresignificantbecausethey--
a.Mustbecollectedtomeetrequirementsoforganizationalpoliciesandprocedures
b.Showthecausesofvariancesandthereasonscertaincorrectiveactionswereselected
c.Showwhycertainprojectswereselectedbytheorganizationoverothers
d.Showwhycertainpeoplewereselectedasprojectmanagerandteammembersoverothers
Qustions4:
Workresultsare--
a.Outcomesofactivitiesperformedtoaccomplishtheproject
b.Successcriteriafortheprojecttomeet
c.Officialverificationofprojectacceptancebythecustomer
d.Officialverificationofcontractcompletion
Qustions6:
Measuringprojectperformanceregularlyisnecessarytoidentifyvariancesfromtheprojectplan.Avarianceisconsideredtobesignificantifit--
a.Isconsideredaprojectrisk
b.Becomesalessonlearnedasaresultofthecorrectiveactionselected
c.jeopardizesprojectobjectives
d.Requirescorrectiveaction
砺志PMP模拟题每周精选之四
(2003年4月7日-2003年4月11日)
Qustions1:
Asappliedtoprojects,temporarymeansthat--
a.Projectsareshortinduration
b.Everyprojecthasadefinitebeginningandend
c.Theundertakingwillendatanundeterminedtimeinthefuture
d.Projectscanbecanceledatanytime
Qustions3:
Whichofthefollowingisanexampleaconstraintinprojectplandevelopment--
a.Recordsfopastperformance
b.Financialreportsfromsimilarprojects
c.Apredefinedbudget
d.Lessonslearnedfrompriorprojects
Qustions5:
Themanagement-by-objectivestechniqueaddressesallthefollowingexcept--
a.Establishingunambiguousandrealisticobjectives
b.Periodicallyevaluatingwhetherprojectobjectiveshavebeenachieved
c.Promotingparticipation,teambuilding,andcommitmenttotheproject
d.Establishingaspecificcareerpathforaprojectteammember
Qustions2:
Allthefollowingareexamplesoftoolsandtechniquesusedinintegrationmanagementexcept--
a.Theworkauthorizationsystem
b.Organizationalprocedures
c.Productskillsandknowledge
d.Organizationalpolicies
Qustions4:
Performancemeasurementtechniquesareusefulinoverallchangecontrolbecausethey--
a.Helpshowthestatusoftheproject
b.Measureoverallprojectprogress
c.Summarizeinformationontheprojectforreportingtostakeholders
d.Helpassesswhethervariancesfromtheplanrequirecorrectiveaction
Qustions6:
Aworkauthorizationsystemisa--
a.Workbreakdownstructureshowingindividualworkelements
b.Formalprocedureforsanctioningworksothatitisdoneattherighttimeinthepropersequence
c.Methodtoensurethateachpersonontheprojectteamknowstheworkelementsthatarehisorherresponsibility
d.Systemtohelpmeasureperformanceintermsofworkcompletedversusworkplanned
砺志PMP模拟题每周精选之三
(2003年3月31日-2003年4月6日)
Qustions1:
Thechangecontrolsystemincludes--
a.Procedurestodefinehowdocumentsmaybechanged
b.Specific