临时用电施工组织设计
目录
1现场勘测··················································1
2确定电源进线、配电室、配电装置、用电设备位置及线路走向···1
3负荷计算··················································3
4.选择变压器················································3
5.设计配电系统···············································4
5.1设计配电线路,选择导线或电缆··························4
5.2设计配电装置,选择电器·································4
5.3设计接地装置············································5
5.4绘制临时用电工程图纸···································5
5.4.1用电工程总平面图····································5
5.4.2接地装置设计图······································5
5.4.3绘制配电系统图······································5
6.设计防雷装置············································5
7.确定防护措施·············································6
8.安全用电技术措施和电气防火措施························6
贯彻JGJ46-2005《施工现场临时用电安全技术规范》,满足施工现场临时用电要求,确保工程的安全顺利施工,根据现场实际情况,特编制本施工现场的临时用电施工组织设计。
1现场勘测
参加人员:
项目经理周培堂、现场电工刘二明、电气工程师李彭波、现场材料员王志强、安全员刘永军等。
建设单位指定施工用变压器位于场地外东南角,电压:
380V、容量:
315KVA
施工现场平面布置:
临建位置,物料堆放;主要用电设备位置见施工现场平面布置图5.4.1
2确定电源进线、变电室、配电装置、用电设备位置及线路走向
2.1施工现场临时用电电源根据勘测情况确定于场地东南角进线,在场地东北角和西侧(大门南)各设1台总配电柜,共2台总配电柜。
按三级配电内容型式布置,即总配电柜——分配电箱——开关箱——用电设备。
配电柜、配电箱、开关箱逐一编号,所运行的开关箱均有专人负责,整个现场有持证电工刘二明按时检查,以防触电等意外伤害事故发生。
2.2电源引入总配电柜后,由总配电柜开始配电,严格按三相五线制(TN—S系统)覆盖施工现场。
做到工作零线与保护零线严格分开。
正常情况下不带电的金属外壳和保护零线相连接,工作零线仅用于负载(即220V照明及220V用电设备使用)。
其中保护零线与其它各导线颜色区别开来,采用绿/黄双色线。
2.3确定分配电箱位置,统计总配电柜所带设备的功率、电压、并选择开关箱列表如下:
总配电箱Z1
设备名称
规格型号
功率KW
数量
功合计
开关箱型号
塔式起重机
QTZ-63
42.2
2
84.4
JSP5-K/3-1-100
闪光对焊机
100
1
100
JSP5-K/4-250
钢筋切断机
GJ-40
7
1
7
JSP5-K/2-63
钢筋调直机
GJ4-14/4
9
1
9
JSP5-K/2-63
钢筋弯曲机
GJ7-40
2.8
1
2.8
JSP5-K/2-63
交流电焊机
21
1
21
JSP5-K/D1-100
合计
224.2Kw
室外照明
10
10
JSP5-K/M1-40
总计
234.2kw
总配电箱Z2
设备名称
规格型号
功率KW
数量
功合计
开关箱型号
塔式起重机
QTZ-63
42.2
1
42.2
JSP5-K/3-100
闪光对焊机
100
1
100
JSP5-K/4-250
钢筋切断机
GJ-40
7
1
7
JSP5-K/2-63
钢筋弯曲机
GJ7-40
2.8
1
2.8
JSP5-K/2-63
交流电焊机
21
1
21
JSP5-K/D1-100
施工电梯
SCD200/200
19
3
57
JSP5-K/2-63
合计
230kw
室内照明
10
10
JSP5-K/M1-40
总计
240kw
2.4确定开关箱位置,每台设备必须有各自的开关箱,严禁用同一个开关箱直接控制2台及2台以上用电设备(含插座)。
3负荷计算
总配电箱Z1负荷为234.2kw;总配电箱Z2负荷为240kw.
将上表数据套入下列公式:
P=1.1×(K1ΣP1+K2ΣP2+K3ΣP3)
P———供电设备需要总容量(KW)
P1——动力用电总容量(KW)
P2——室外照明总功率(KW)
P3——室内生活、照明总功率(KW)
K1——全部施工用电同时系数:
取0.7
K2——室外照明设备同时系数:
取1.0
K3——室内生活、照明需用系数:
取0.8
得Pz1=1.1×(0.70×224.2+1×10)=183.64(KW)
Pz2=1.1×(0.70×230+0.8×10)=185.9(KW)
4.变压器选择
根据以上计算总的用电量选择变压器,现在建设单位已指定电源,核实电源提供的容量是否满足要求。
变压器容量按下式计算:
P总=K(PZ1+PZ2)=0.7×(183.64+185.9)=258.68KW(施工同时系数取0.7)
Pb=1.05P总/cosФ=1.05×258.68/0.9=301.8KVA
结论:
315KVA变压器基本满足要求。
注;因为施工用变压器有电容补偿装置,故cosФ取0.9
5配电系统设计
5.1设计配电线路
选择导线或电缆先按电缆安全载流量选择导线截面,然后用电压损失条件进行校验。
根据总配电箱1设备总功率选择导线。
总配电箱1所带设备计算电缆截面。
将以上数据套入下列公式:
Px=P1=1.1×(0.70×224.2+1×10)=183.64(KW)
①按电缆安全载流量选择:
将Px带入下式:
I=Px/cosФ[
×Ue]
I——电流A
Px——线路输送的电功率W
cosФ——功率因数0.9
Ue——额定电压380V
得I=183640/(0.9×1.732×380)=310A查电缆载流量表得电缆截面YJV-120mm2的载流量为300A,综合考虑使用情况及经济因素,选择该型号电缆。
②按电压降校验:
将Px带入下式
S=ΣI×L/(C×ε)
S————导线面积(mm2)
I————线路输送的电流A
L————送电线路的距离m
ε————允许电路损失5%
C————系数为77
得S=310.0×100/(77×5)=80.5mm2<120mm2故应选用YJV22-3×120+2×70电缆.
按以上计算方法,按总配电箱2所带设备计算电缆截面:
选用YJV22-3×120+2×70电缆。
5.1.1根据每台设备容量按以上方法计算的结果选择从设备到开关箱的导线或电缆;
如:
起重机42.2KW额定电流I=42200/(0.9×1.732×380)71.24A,查表得电缆截面为YJV22-3×25+2×16mm2,S=ΣI×L/(C×ε)=71.24A×50m/(77×5)=9.25mm2<25mm2,故电缆选择YJV22-3*25+2*16。
施工电梯19KW额定电流I=19000/(0.9×1.732×380)=32.08A,查表得电缆截面为YJV22-3×10+2×6mm2,S=ΣI×L/(C×ε)=32.08A×50m/(77×5)=4.16mm2<10mm2,故电缆选择YJV22-3*10+2*6。
5.1.2根据每个开关箱所带设备容量按以上方法计算的结果选择从开关箱到分配电箱的导线或电缆;
5.1.3根据每个分配电箱所带设备容量按以上方法计算的结果选择从分配电箱到总配电箱的导线或电缆;
如分箱F11所带设备为塔吊2台84.4KW额定电流I=84400×0.8/(0.9×1.732×380)=113.9A,查表得电缆截面为YJV22-3×50+2×25mm2,S=ΣI×L/(C×ε)=113.9A×50m/(77×5)=14.7mm2<50mm2,故电缆选择YJV22-3*50+2*25。
如分箱F21所带设备为施工电梯3台57KW额定电流I=57000×0.8/(0.9×1.732×380)=76.98A,查表得电缆截面为YJV22-3×25+2×10mm2,S=ΣI×L/(C×ε)=76.98A×50m/(77×5)=9.9mm2<50mm2,故电缆选择YJV22-3*25+2*10。
5.2设计配电装置,选择成套配电箱。
根据以上计算结果,确定主要线路电缆规格如下:
总配电柜Z1
序号
线缆规格型号
起点
终点
长度m
1
YJV-3*120+2*70
电源变压器
总柜(Z1)
50
2
YJV-3*50+2*25
总柜(Z1)
塔吊分配箱(F11)
50
3
YJV-3*70+2*25
总柜(Z1)
闪光对焊机(K13)
40
4
YJV-3*25+2*16
总柜(Z1)
分配电箱(F12)
30
5
YJV-3*16+2*10
总柜(Z1)
电焊机(K14)
30
6
YJV-3*25+2*16
塔吊分配箱(F11)
塔吊开关箱(K11K12)
30
7
YC-5*4
分配电箱(F12)
切断机(K15)
10
8
YC-5*4
分配电箱(F12)
弯曲机(K16)
25
9
YC-5*4
分配电箱(F12)
调直机(K17)
25
10
YC-2*10+1*6
总柜(Z1)
照明箱(K18)
总配电柜Z2
1
YJV-3*120+2*70
电源变压器
总柜(Z2)
150
2
YJV-3*25+2*16
总柜(Z2)
塔吊开关箱(K21)
60
3
YJV-3*70+2*25
总柜(Z2)
闪光对焊机(K22)
50
4
YJV-3*25+2*16
总柜(Z2)
分配电箱(F21)
30
5
YJV-3*25+2*16
总柜(Z2)
分配电箱(F22)
50
6
YJV-3*10+2*6
分配电箱(F21)
施工电梯(K23K24K25)
50
7
YJV-3*16+2*10
分配电箱(F22)
电焊机(K26)
30
8
YC-5*4
分配电箱(F22)
切断机(K27)
15
9
YC-5*4
分配电箱(F22)
弯曲机(K28)
20
10
YC-2*10+1*6
总柜(Z2)
照明箱(K29)
60
5.3接地装置设计
5.3.1接地体采用人工接地体和人工接地线。
工作接地:
Φ25镀锌圆钢2500长接地极三根,间距5米,用-40*40镀锌扁钢连接,接头处采用搭接焊,焊接不少于3面。
重复接地:
土壤电阻率ρ=1000Ωm以下时,采用Φ25镀锌圆钢2500长接地极,作法同上。
5.3.2保护零线:
每一重复接地装置的接地电阻值不大于10Ω,人工接地线采用塑套绝缘铜线,截面为10mm2,每一接地装置的接地线应采用二根以上导体,在不同点与接地装置做电气链接。
电源变压器已经做了工作和避雷接地,为保证施工现场内电力系统的正常运行,再在总配电柜处设重复接地装置,接地电阻值不得大于4欧姆。
若现场测试达不到要求,再增加接地极数量。
接地装置做法如图5.4.2
5.4用电工程总平面图:
根据施工现场条件及工程需要,绘制用电平面图5.4.1
5.5根据总、分配电情况,绘制配电系统图5.4.2
6.设计防雷装置
6.1避雷针采用Φ20的镀锌圆钢,长度为1-2m,顶端用砂轮磨尖,设置于塔吊顶端,由于塔吊顶端避雷针按60°角计算的保护范围能够保护其他设备,且最后退场,所以其他设备(包括脚手架)可不设防雷装置。
6.2现场内的防雷装置和需作防雷接地的部位,均应经过防雷接地引下线与防雷接地体作电气连接,防雷接地引下线采用镀锌圆钢搭接焊,保证电气连接
7.确定防护措施
7.1外电线路的防护:
本工程A2区南侧路边有一条10KV高压线,为保证施工安全严格按《施工现场临时用电安全技术规范》进行防护(五公司施工范围)。
7.2电气设备防护:
电气设备周围严禁存放易燃易爆等物资;避免物体坠落和机械损伤。
7.3架空线路施工:
本工程不使用架空线路,若必须架空时严格按《施工现场临时用电安全技术规范》、《建设工程施工现场供用电安全规范》进行施工。
7.4电缆线路施工:
需要三相四线制配电的电缆线路必须采用五芯电缆,直埋敷设深度不小于0.7米且按规范铺沙盖砖并做好标志。
7.5室内配线:
导线或电缆截面按用电负荷计算结果确定且不小于1.5mm2,必须从配电箱内相应的断路器引出,插座回路必须从相应的漏电断路器引出。
8.安全用电技术措施和电气防火措施
8.1安全用电技术措施
8.1.1保证正确可靠的保护接地与接零:
在施工现场专用的中性点直接接地的低压线路中采用TN-S接零保护系统。
8.1.2.配置漏电保护器
施工现场的配电箱和开关箱为三级配电,二级保护。
8.1.3停电、检修:
a.悬挂停电标志牌,设专人看护电闸;
b.由专业电工检修;
c.检修人员穿戴绝缘鞋和手套,使用电工绝缘工具;
8.1.4对混凝土搅拌机、钢筋加工机械、木工机械、等设备进行清理、检查、维修时,必须首先首先将其开关箱分闸断电,呈现可见电源分断点,并关门上锁。
8.2安全用电管理制度:
详见集团公司《施工现场安全管理程序》施工用电部分
8.2.1技术交底制度:
向专业电工、各类用电人员介绍临时用电施工组织设计和安全用电技术措施的总体意图、技术内容和注意事项,并在技术交底和文字资料上履行交底人和被交底人的签字手续,载明交底日期。
8.2.3安全检测制度:
从临时用电工程开工开始,定期对临时用电工程进行检测,主要内容是:
接电阻值、电器设备绝缘电阻值每月一次、漏电保护器动作每天一次,并做好检测记录,对检查出的隐患马上处理,并履行复查验收手续,保证临时用电工程安全可靠。
8.2.4电气维修制度:
加强日常和定期维修工作,及时发现和清除隐患,并建立维修工作记录,记载维修时间、地点、设备、内容、技术措施、处理结果、维修人员、验收人员等。
8.2.5安全用电负责制度:
对临时用电工程各部位的操作、监护、维修、分片、分块、分机落实到人,并辅以必要的奖罚。
8.3电气防火措施:
8.3.1合理配置、整定、更换各种保护电器,对电路和设备的过载、短路故障进行可靠的保护。
8.3.2在电器装置的和线路周围不堆放易燃、易爆和腐蚀介质,不使用火源,合理配置防火器材,每个开关箱侧适当位置放置一个手提式泡沫灭火器。
8.3.3加强电气防火重点场所烟火管制,并在场区内重要岗位和防火区域设置“禁止烟火”标志。
8.3.4建立电气防火检查制度,现场电工定期、项目经理不定期巡回检查,并做好检查记录,发现问题及时处理。
8.3.5建立安全技术档案并包括下列内容:
1用电组织设计的全部资料;
2修改用电组织设计的资料;
3用电技术交底资料;
4用电工程检查验收表;
5电气设备的试、检验凭单和调试记录;
6接地电阻、绝缘电阻和漏电保护器漏电动作参数测定记录表;
7定期检(复)查表;
8电工安装、巡查、维修、拆除工作记录。
接地装置图5.4.2
图5.4.3配电系统图: